A devastating report from the public spending watchdog has said it [the IT programme created to control UC] has been beset by "weak management, ineffective control and poor governance". The National Audit Office said the government had embarked on the flagship project without knowing how it would work. We are back to the bad old days where projects are not given tests to prove whether they are worthy of development. Although it appears it is even worse than that and for the last three years the only reports coming out of the IT team have been good ones where all the bad news has been suppressed. How is this not corruption?

A lot of figures have been thrown round today and I do not have access to the inside details, but when a government body produces a report that states the left hand has no idea what the right hand is doing and the mind in the middle has given permission for a project to proceed where there is no path for it to follow, it beggars the question who knows what and why are you spending tax payers money on it?

The auditors found the IT system could not identify potentially fraudulent claims, meaning manual checks were needed on claims and payments. "Such checks will not be feasible or adequate once the system is running nationally".

Citizens Advice chief executive Gillian Guy said: "Even as Universal Credit is being rolled out, we still do not know what support will be put in place to help people to move on to the new system." <<< more disaster waiting to happen…

No comments:

Post a Comment